Description: | Minimum number of units automatically constructed in aggregate over the planning horizon |
Facility Min Units Built requires that a certain number of units are built by LT Plan over the course of the planning horizon. This number must be less than or equal to Max Units Built.
Property | Value | Units |
---|---|---|
Units | 0 | - |
Max Operating Level | 500 | - |
FO&M Charge | 25,000,000 | $ |
Max Units Built | 1 | - |
Min Units Built | 1 | - |
Build Cost | 750,000,000 | $ |
Economic Life | 25 | years |
WACC | 10 | % |
In this example, one unit must be built at some time in the planning
horizon. Note that you can control the timing of the build using Date
From on the Max
Units Built.