Generator Commission Date

Units:-
Mode:Input Only
Multi-band:False
Default Value:1
Validation Rule:≥0
Key Property:No
Description:Date the generator was commissioned for use with [Technical Life]

Generator Commission Date is the date the facility was commissioned. When combined with Technical Life it sets the retirement date for the facility.  This property only works for when Units = 1 as in the example in Table 1.

Table 1: Commission Date Example
Property Value Units
Units 1 -
Max Capacity 500 MW
Commission Date 1/1/1970 -
Technical Life 30 yr

In this example the facility will retire at the start of 2000.

Note that this property is ignored if any of the following properties are defined: