Units: | $/GWh |
Mode: | Input Only |
Multi-band: | False |
Default Value: | 10000000 |
Validation Rule: | Any Value |
Key Property: | No |
Description: | Penalty applied to violations of [Min Energy] and [Min Capacity Factor] constraints. |
Generator Min Energy Penalty is the penalty applied to violations of the Min Energy or Min Capacity Factor constraints and its period-specific variants. The penalty is per gigawatt-hour hence the default implies a penalty per megawatt-hour of $10000. A value of -1 makes this a hard constraint.