Generator Min Units Built

Units:-
Mode:Input Only
Multi-band:False
Default Value:0
Validation Rule:≥0
Key Property:No
Description:Minimum number of units automatically constructed in aggregate over the planning horizon

Generator Min Units Built requires that a certain number of unit are built by LT Plan over the course of the planning horizon. This number must be less than or equal to Max Units Built.

Note: The Max Units Built property must be defined for expansion candidates, otherwise the LT Plan will build no units by default.

Table 1: Min Units Built Example
Property Value Units
Units 0 -
Max Capacity 500 MW
FO&M Charge 50 $/kW/year
Max Units Built 1 -
Min Units Built 1 -
Build Cost 1500 $/kW
Economic Life 25 years
WACC 10 %

In this example, one unit must be built at some time in the planning horizon. Note that you can control the timing of the build using Date From on the Max Units Built.