Line Project Start Date

Units:-
Mode:Input Only
Multi-band:False
Default Value:36526
Validation Rule:≥0
Key Property:No
Description:Start date of transmission project, for expansion planning.

Line Project Start Date is first date after which the transmission project can be constructed in LT Plan.

This input is an integer representing a date in Microsoft date format, which is the number of days since 1/01/1900 (January 1, 1900). The default value of 36526 is the date 1/01/2000.

Example

Line Property Value Units
X-Y Units 0 -
X-Y Max Flow 150 MW
X-Y Max Units Built 1 -
X-Y Project Start Date 1/01/2012 -
X-Y Build Cost 2000 $000
X-Y Economic Life 35 years
X-Y WACC 8 %

In the above example, the Line cannot be constructed before the year 2012, which has date number 40909.

TIP: To work out the date number that applies to a given date, enter the date into a cell in Microsoft Excel and change the number format of the cell to "General". This will then show the date its underlying number representation.

See also: Line Max Units Built.