Detail:

Facility Levelized Cost isĀ  is a measure of the average net present cost of electricity Production for a facility over its lifetime. It is used for investment planning and to compare different methods of electricity Production on a consistent basis. The LCE "represents the average revenue per unit of electricity generated that would be required to recover the costs of building and operating a generating plant during an assumed financial life and duty cycle", and is calculated as the ratio between all the discounted costs over the lifetime of an electricity generating plant divided by a discounted sum of the actual energy amounts delivered

The value reported here is It is calculated as:

Levelized Cost = Total Cost / Production

The Total Cost is the raw value without discounting, thus to compute the true LCE you should apply discounting.