Heat Plant Units Producing Heat
Units: | - |
Mode: | Output Only |
Multi-band: | False |
Default Value: | |
Validation Rule: | |
Key Property: | No |
Description: | Number of units producing heat |
Detail: |
This is the number of units producing heat i.e. that are on-line and generating heat. A unit is counted as being 'online' once it has been started and is generating above notional zero level i.e. this includes any run up/down period.
By default, he simulation will freely choose the initial commitment state of the units on/off depending on which is optimal.
Units Producing Heat will be a value between zero and the number of Units plus any Units Built (in LT Plan). It will be an integer only if:
- The Production Unit Commitment Optimality setting is not "Linear Relaxation"; and
- The Heat plant Unit Commitment Optimality setting is also not "Linear Relaxation"; and
- The simulation phase is ST Schedule (chronological simulation).
In all other cases Units Producing Heat can be non-integer.
See also: