Charging Station Index
Charging Station Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Build Cost | $ | True | 0 | False | Cost of building a unit | |
Charge Efficiency | % | False | 100 | Between 0 And 100 | False | Efficiency of charging |
Deferment Period | h | True | 0 | ≥0 | False | Length of time load is deferred where zero means one interval |
Deferrable Load | % | True | 0 | ≥0 | False | Proportion of charging load that can be deferred |
Discharge Efficiency | % | False | 100 | Between 0 And 100 | False | Efficiency of discharging |
Economic Life | yr | False | 30 | ≥0 | False | Economic life of the unit (period over which fixed costs are recovered) |
Expansion Optimality | - | False | 2 | In (0,2) | False | Expansion planning integerization scheme. |
Fixed Generation | MW | False | 0 | ≥0 | False | Fixed generation across all units |
Fixed Load | MW | False | 0 | ≥0 | False | Fixed charging load across all units |
FO&M Charge | $ | False | 0 | False | Annual fixed operation and maintenance charge | |
Max Charge Rate | kW | False | 1E+30 | False | Maximum charge rate | |
Max Discharge Rate | kW | False | 1E+30 | False | Maximum discharge rate | |
Max Generation | MW | False | 0 | ≥0 | False | Maximum generation across all units |
Max Load | MW | False | 0 | ≥0 | False | Maximum charging load across all units |
Max Units Built | - | False | 0 | ≥0 | False | Maximum number of units automatically constructed in aggregate over the planning horizon |
Max Units Built in Year | - | False | 1E+30 | ≥0 | False | Maximum number of units automatically constructed in any single year of the planning horizon |
Max Units Retired | - | False | 0 | ≥0 | False | Maximum number of units automatically retired in aggregate over the planning horizon |
Max Units Retired in Year | - | False | 1E+30 | ≥0 | False | Maximum number of units automatically retired in any single year of the planning horizon |
Min Generation | MW | False | 0 | ≥0 | False | Minimum generation across all units |
Min Load | MW | False | 0 | ≥0 | False | Minimum charging load across all units |
Min Units Built | - | False | 0 | ≥0 | False | Minimum number of units automatically constructed in aggregate over the planning horizon |
Min Units Built in Year | - | False | 0 | ≥0 | False | Minimum number of units automatically constructed in any single year of the planning horizon |
Min Units Retired | - | False | 0 | ≥0 | False | Minimum number of units automatically retired in aggregate over the planning horizon |
Min Units Retired in Year | - | False | 0 | ≥0 | False | Minimum number of units automatically retired in any single year of the planning horizon |
Project Start Date | - | False | 36526 | ≥0 | False | Start date of generation project, for expansion planning |
Retirement Cost | $ | False | 0 | False | Cost of retiring a unit | |
Technical Life | yr | False | 1E+30 | ≥0 | False | Technical lifetime of the unit |
Units | - | False | 0 | ≥0 | True | Number of chargers |
UoS Charge | $/MWh | False | 0 | False | Use of system charge | |
WACC | % | False | 10 | ≥0 | False | Weighted average cost of capital |
x | - | True | 0 | False | Value to pass-through to solution | |
y | - | True | 0 | False | Value to pass-through to solution | |
z | - | True | 0 | False | Value to pass-through to solution |
Charging Station Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Annualized Build Cost - $000 | Annualized Build Cost - $000 | Expansion | LT Plan | False | Annualized cost of units built |
Build Cost - $000 | Build Cost - $000 | Expansion | LT Plan | False | Cost of building a unit |
Capacity Built - kW | Capacity Built - kW | Expansion | LT Plan | False | Capacity built |
Capacity Retired - kW | Capacity Retired - kW | Expansion | LT Plan | False | Capacity retired |
Charge Cost - $ | Charge Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Cost of charging |
Charge Price - c/kWh | Charge Price - c/kWh | Production | LT Plan, MT Schedule, ST Schedule | False | Price paid charging |
Charging - kW | Charging - MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Load from charging |
Deferred Load - kW | Deferred Load - MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Deferred charging load |
Discharge Price - c/kWh | Discharge Price - c/kWh | Production | LT Plan, MT Schedule, ST Schedule | False | Price received discharging |
Discharge Revenue - $ | Discharge Revenue - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Revenue from discharging |
Discharging - kW | Discharging - MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Generation from discharging |
FO&M Cost - $ | FO&M Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Fixed operation and maintenance cost |
Hours Deferred - h | Hours Deferred - h | Production | LT Plan, MT Schedule, ST Schedule | False | Average hours load is deferred in the period |
Inertia - MW·s | Inertia - GW·s | Production | LT Plan, MT Schedule, ST Schedule | False | Provision of inertia |
Installed Capacity - kW | Installed Capacity - kW | Production | LT Plan, PASA, MT Schedule, ST Schedule | False | Total charging capacity of the station |
Losses - kW | Losses - MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Total charge and discharge losses |
Lower Reserve - kW | Lower Reserve - MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Provision of lower (spin down) reserve |
Net Charge Cost - $ | Net Charge Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Net of cost of charging and revenue from discharging |
Raise Reserve - kW | Raise Reserve - MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Provision of raise (spin up) reserve |
Regulation Lower Reserve - kW | Regulation Lower Reserve - MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Provision of regulation lower reserve |
Regulation Raise Reserve - kW | Regulation Raise Reserve - MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Provision of regulation raise reserve |
Replacement Reserve - kW | Replacement Reserve - MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Provision of replacement reserve |
Reserves Revenue - $ | Reserves Revenue - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Revenue from provision of reserves |
Retirement Cost - $000 | Retirement Cost - $000 | Expansion | LT Plan | False | Cost of retiring a unit |
Total Cost - $000 | Total Cost - $000 | Expansion | LT Plan | False | Total of fixed and variable costs |
Units | Units | Production | LT Plan, MT Schedule, ST Schedule | False | Number of chargers |
Units Built | Units Built | Expansion | LT Plan | False | Number of units built |
Units Retired | Units Retired | Expansion | LT Plan | False | Number of units retired |
UoS Cost - $ | UoS Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Total use of system cost |
x | x | Pass-through | LT Plan, MT Schedule, ST Schedule | True | Value to pass-through to solution |
y | y | Pass-through | LT Plan, MT Schedule, ST Schedule | True | Value to pass-through to solution |
z | z | Pass-through | LT Plan, MT Schedule, ST Schedule | True | Value to pass-through to solution |