Waterway Index
Waterway Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Flow Control | - | False | 0 | In (0,1) | False | Waterway flow optimization method (0=economic, 1=flow when spilling only) |
Initial Flow | MW | False | 0 | ≥0 | False | Initial flow on the waterway for use in enforcing first period ramp constraint. |
Input Scalar | - | False | 1 | False | Input flow scalar | |
Max Flow | MW | False | 1E+30 | ≥0 | False | Maximum flow limit |
Max Flow Penalty | $/MW | False | -1 | ≥-1 | False | Penalty for violating the [Max Flow] constraint. |
Max Ramp | MW | False | 1E+30 | ≥0 | False | Maximum change in flow (MW or cumecs per hour) |
Max Ramp Penalty | $/MW | False | -1 | ≥-1 | False | Penalty for violating the [Max Ramp] constraint. |
Min Flow | MW | False | 0 | ≥0 | False | Minimum flow limit |
Min Flow Penalty | $/MW | False | -1 | ≥-1 | False | Penalty for violating the [Min Flow] constraint. |
Output Scalar | - | False | 1 | False | Output flow scalar | |
Traversal Time | h | False | 0 | ≥0 | False | Time taken for flows to traverse the waterway |
x | - | True | 0 | False | Value to pass-through to solution | |
y | - | True | 0 | False | Value to pass-through to solution | |
z | - | True | 0 | False | Value to pass-through to solution |
Waterway Constraints Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Flow Coefficient | MW | False | 0 | False | Coefficient of waterway flow. | |
Hours Flowing Coefficient | h | False | 0 | False | Coefficient of the number of hours the waterway is flowing | |
Ramp Coefficient | MW | False | 0 | False | Coefficient of change in waterway flow. |
Waterway Objectives Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Flow Coefficient | MW | False | 0 | False | Coefficient of waterway flow | |
Hours Flowing Coefficient | h | False | 0 | False | Coefficient of the number of hours the waterway is flowing | |
Ramp Coefficient | MW | False | 0 | False | Coefficient of change in waterway flow |
Waterway Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Flow - MW | Flow - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Flow on waterway |
Hours Flowing - h | Hours Flowing - h | Production | LT Plan, MT Schedule, ST Schedule | False | Number of hours the waterway is flowing |
Max Flow - MW | Max Flow - MW | Production | LT Plan, MT Schedule, ST Schedule | False | Maximum flow limit |
Max Flow Violation - MW | Max Flow Violation - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Violation of max flow constraint |
Max Flow Violation Cost - $ | Max Flow Violation Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Cost of [Max Flow] violations. |
Max Flow Violation Hours - h | Max Flow Violation Hours - h | Production | LT Plan, MT Schedule, ST Schedule | False | Number of hours the [Max Flow] limit is violated. |
Max Ramp - MW | Production | LT Plan, MT Schedule, ST Schedule | False | Maximum change in flow (MW or cumecs per hour) | |
Min Flow - MW | Min Flow - MW | Production | LT Plan, MT Schedule, ST Schedule | False | Minimum flow limit |
Min Flow Violation - MW | Min Flow Violation - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Violation of min flow constraint |
Min Flow Violation Cost - $ | Min Flow Violation Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Cost of [Min Flow] violations. |
Min Flow Violation Hours - h | Min Flow Violation Hours - h | Production | LT Plan, MT Schedule, ST Schedule | False | Number of hours the [Min Flow] limit is violated. |
Ramp - MW | Ramp - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Change in flow |
Ramp Violation - MW | Ramp Violation - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Violation of flow ramp constraint |
Ramp Violation Cost - $ | Ramp Violation Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Cost of [Max Ramp] constraint violations. |
Ramp Violation Hours - h | Ramp Violation Hours - h | Production | LT Plan, MT Schedule, ST Schedule | False | Number of hours the [Max Ramp] constraint is violated. |
Shadow Price - $/MW | Shadow Price - $/MW | Production | LT Plan, MT Schedule, ST Schedule | False | Shadow price on max flow constraint |
x | x | Pass-through | LT Plan, MT Schedule, ST Schedule | True | Value to pass-through to solution |
y | y | Pass-through | LT Plan, MT Schedule, ST Schedule | True | Value to pass-through to solution |
z | z | Pass-through | LT Plan, MT Schedule, ST Schedule | True | Value to pass-through to solution |