Line Min Units Built in Year

Units: -
Mode: Input Only
Multi-band: False
Default Value: 0
Validation Rule: In (0,1)
Key Property: No
Description: Minimum number of units automatically constructed in any single year of the planning horizon
Detail:

Line Min Units Built in Year forces the building of the Line by LT Plan in a particular year of the planning horizon.

Example

Line Property Value Units Date From Date To
X-Y Units 0 -
X-Y Max Flow 150 MW
X-Y Max Units Built 1 -
X-Y Min Units Built in Year 1 - 1/01/2012 31/12/2012
X-Y Build Cost 2000 $000
X-Y Economic Life 35 years
X-Y WACC 8 %

Note that Min Units Built in Year must be compatible with Line Max Units Builti.e. the Line must be allowed to be built.

See also: Line Max Units Built in Year.