Units:
|
- |
Mode:
|
Input Only |
Multi-band:
|
False |
Default Value:
|
1 |
Validation Rule:
|
Between 0 And 1 |
Key Property:
|
No |
Description:
|
Proportion of company load that occurs at a node |
Detail:
|
|
Load Load Participation Factor is the proportion of Company Load that occurs at a node. Let's say that a company (Company_1) serves three customers Load_1, Load_2, and Load_3 at nodes Node_1, Node_2, and Node_3, respectively. Let the total load served by the company be equal to 100 MW and Load_1, Load_2, Load_3 be 30 MW, 20 MW, and 50 MW, respectively.
The following example shows how to input the above data using Company and Load.
Company |
Property |
Value |
Datafile |
Units |
Band |
Date From |
Date To |
Timeslice |
Company_1 |
Load |
100 |
|
MW |
1 |
|
|
|
Load |
Property |
Value |
Datafile |
Units |
Band |
Date From |
Date To |
Timeslice |
Load_1 |
Load Participation Factor |
0.3 |
|
- |
1 |
|
|
|
Load_2 |
Load Participation Factor |
0.2 |
|
- |
1 |
|
|
|
Load_3 |
Load Participation Factor |
0.5 |
|
- |
1 |
|
|
|