Stochastic EFOR Maintenance Adjust

Units: Yes/No
Default Value: False (0)
Validation Rule: False (0) or True (-1)
Description: Adjust EFOR to account for Units Out
Detail:

This property applies to all outage facilities such as Generator, Line, Gas Pipeline. It controls the interaction between Forced Outage Rate and planned maintenance defined with Units Out. By default Forced Outage Rate is interpreted as the mean percentage of all hours of the year that the facility is unexpectedly out-of-service. Switching this parameter to true changes this interpretation to be the percentage of in-service hours rather than all hours.

For example, if one defines the following properties:

Generator Property Value Data File Units Band Date From Date To
Coal Forced Outage Rate 10 % 1
Coal Units Out 1 - 1 Sunday, 1 March 2015 00:00:00 Sunday, 31 May 2015 00:00:00

By default the unit is expected to be forced out for 0.1 × 8760 = 876 hours in the year. With the parameter toggled to true the unit is expected out 0.1 × (8760 - 92 × 24) = 655.2 hours, the difference being the amount of time on scheduled maintenance.