Company Dump Energy Allocation

Units:MW
Mode:Output Only
Multi-band:False
Default Value:
Validation Rule:
Key Property:No
Description:Dump energy allocated to the company.

Company Dump Energy Allocation is Dump energy allocated to the company..

Following example shows dump energy allocation: Demand at node N1 is allocated from 3 company objects as follows:
Company Demand allocation (MW)
C1 (via load object L1) 10
C2 (via load object L2) 15
C3 (via load object L3) 20
If 5 MW of Dump Energy occurred at Node N1, then it is allocated to Company C1, C2, C3 as follows:
Company Dump Energy allocation (MW)
C1 1.11
C2 1.66
C3 2.22