Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
ORDC MCL | MW | False | 0 | False | Minimum Contingency Level for ORDC calculations | |
ORDC Schedule Mu | MW | False | 0 | False | Average of the forecasted hourly reserve value for ORDC calculations | |
ORDC Schedule Sigma | MW | False | 0 | False | Standard deviation of the forecasted hourly reserve value for ORDC calculations | |
ORDC VOLL | $/MWh | False | 0 | False | Value of Lost Load for ORDC calculations | |
x | - | True | 0 | False | Value to pass-through to solution | |
y | - | True | 0 | False | Value to pass-through to solution | |
z | - | True | 0 | False | Value to pass-through to solution |
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Balancing Area Interchange Hurdle | $/MWh | False | 0 | False | Financial hurdle rate for exports from the regions in the pool | |
Max Balancing Area Interchange | MW | False | 1E+30 | False | Maximum financial exports for regions in the Pool |
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Cost of Dump Energy - $ | Cost of Dump Energy - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Cost of dump energy. |
Cost of Unserved Energy - $ | Cost of Unserved Energy - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Cost of unserved energy. |
Cost to Load - $ | Cost to Load - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Cost to load of their energy purchases |
Customer Load - MW | Customer Load - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Total customer load |
Dump Energy - MW | Dump Energy - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Dump energy |
Export Cost - $ | Export Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Cost of exports |
Exports - MW | Exports - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Exports |
Generation - MW | Generation - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Generation |
Generation-weighted Price - $/MWh | Generation-weighted Price - $/MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Generation-weighted average price |
Generator Pool Revenue - $ | Generator Pool Revenue - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Total generator pool revenue |
Import Revenue - $ | Import Revenue - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Revenue from imports |
Imports - MW | Imports - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Imports |
Load - MW | Load - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Total load |
Load-weighted Price - $/MWh | Load-weighted Price - $/MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Load-weighted average price |
Net Generation - MW | Net Generation - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Net generation value |
ORDC Offline Price Adder - $/MWh | ORDC Offline Price Adder - $/MWh | Production | LT Plan, MT Schedule, ST Schedule | False | ORDC Offline Price Adder |
ORDC Online Price Adder - $/MWh | ORDC Online Price Adder - $/MWh | Production | LT Plan, MT Schedule, ST Schedule | False | ORDC Online Price Adder |
ORDC System Lambda - $/MWh | ORDC System Lambda - $/MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Max value of Energy Charge over all Nodes |
Price - $/MWh | Price - $/MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Energy price |
Total Generation Cost - $ | Total Generation Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Total of generation,start, shutdown, and emissions costs |
Transmission Losses - MW | Transmission Losses - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Total transmission losses |
Unserved Energy - MW | Unserved Energy - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Unserved energy (USE) |
x | x | Pass-through | LT Plan, PASA, MT Schedule, ST Schedule | True | Value to pass-through to solution |
y | y | Pass-through | LT Plan, PASA, MT Schedule, ST Schedule | True | Value to pass-through to solution |
z | z | Pass-through | LT Plan, PASA, MT Schedule, ST Schedule | True | Value to pass-through to solution |