Units: | - |
Mode: | Input Only |
Multi-band: | False |
Default Value: | 0 |
Validation Rule: | Any Value |
Key Property: | No |
Description: | Right hand side each month (000) |
Constraint RHS Month defines the right-hand side (constant) term for each month of the planning horizon. Setting this property defines the period of the constraint as one constraint per month.
NOTE: In most cases for RHS Day/Week/Month/Year/Custom, the RHS scalar is 1000. However, there are some exceptions where the RHS scalar is 1. The exceptions include all non-quantity constraints, all gas constraints, Maintenance Min Occurrence constraints, constraints related to Storages (with End Volume/End Level/Ramp Coefficient) / Waterways (with Ramp Coefficient) / Maintenances (with Start Hour Coefficient) / Generators (with Capacity Factor Coefficient or only defined interval Units Started/Units Shutdown/Units Generating/Operating Hours/Pump Operating Hours Coefficient), constraints using expansion, and constraints not using activities.