Heat Plant Index

Heat Plant Input Properties

NameUnitsMulti-bandDefault ValueValidation RuleKey PropertyDescription
Build Cost$000True0FalseCost of building a unit
Build Non-anticipativity$/MWFalse-1FalsePrice for violating non-anticipativity constraints in scenario-wise decomposition mode
Economic LifeyrFalse30≥0FalseEconomic life of the Heat Plant (period over which fixed costs are recovered).
Efficiency BaseGJ (Metric), MMBtu (U.S. Imperial)True0FalseHeat production no-load efficiency
Efficiency IncrGJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)True1FalseHeat production efficiency
Expansion Optimality-False0In (0,2)FalseExpansion planning integerization scheme.
FO&M Charge$000False0FalseAnnual fixed operation and maintenance charge
Heat RateGJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)True0≥0FalseAverage heat rate (total fuel divided by total heat production)
Heat Rate BaseGJ/h (Metric), MMBtu/h (U.S. Imperial)False0≥0FalseConstant term in fuel use function (no-load cost)
Heat Rate IncrGJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)True1≥0FalseFirst-order polynomial term in unit fuel use function (marginal heat rate)
Integerization HorizonyrFalse-1≥-1FalseNumber of years over which the expansion decisions are integerized
Lead TimeyrFalse0≥0FalseNumber of years after which the expansion project can begin
Load PointGJ (Metric), MMBtu (U.S. Imperial)True0≥0FalseLoad point for use with multi-point heat rate.
Max CapacityGJ/h (Metric), MMBtu/h (U.S. Imperial)False0FalseMaximum heat production
Max Down TimehFalse0≥0FalseMaximum number of hours a unit can be off after being shut down
Max Ramp DownGJ/h (Metric), MMBtu/h (U.S. Imperial)False1E+30≥0FalseMaximum ramp down rate
Max Ramp UpGJ/h (Metric), MMBtu/h (U.S. Imperial)False1E+30≥0FalseMaximum ramp up rate
Max Units Built-False0≥0FalseMaximum number of units automatically constructed in aggregate over the planning horizon
Max Units Built in Year-False1≥0FalseMaximum number of units automatically constructed in any single year of the planning horizon
Max Units Retired-False0≥0FalseMaximum number of units automatically retired in aggregate over the planning horizon
Max Units Retired in Year-False1≥0FalseMaximum number of units automatically retired in any single year of the planning horizon
Max Up TimehFalse0≥0FalseMaximum number of hours a unit can be run after being started
Min Down TimehFalse0≥0FalseMinimum number of hours a unit must be off after being shut down
Min Stable LevelGJ (Metric), MMBtu (U.S. Imperial)False0≥0FalseMinimum stable Heat Production level
Min Units Built-False0≥0FalseMinimum number of units automatically constructed in aggregate over the planning horizon
Min Units Built in Year-False0≥0FalseMinimum number of units automatically constructed in any single year of the planning horizon
Min Units Retired-False0≥0FalseMinimum number of units automatically retired in aggregate over the planning horizon
Min Units Retired in Year-False0≥0FalseMinimum number of units automatically retired in any single year of the planning horizon
Min Up TimehFalse0≥0FalseMinimum number of hours a unit must be run after being started
Project Start Date-False36526≥0FalseStart date of gas node project, for expansion planning.
Retire Non-anticipativity$/MWFalse-1FalsePrice for violating non-anticipativity constraints in scenario-wise decomposition mode
Retirement Cost$000False0FalseCost of retiring the Heat Plant
Run Up RateGJ/h (Metric), MMBtu/h (U.S. Imperial)True1E+30≥0FalseRamp rate that applies while running the unit up from zero to [Min Stable Level].
Start Cost$True0≥0FalseCost of starting a unit
Start Cost TimehTrue0≥0FalseIncremental cooling time over which the corresponding Start Cost applies
Start ProfileGJ (Metric), MMBtu (U.S. Imperial)True1E+30FalseDetailed regime for running the unit up from zero to [Min Stable Level] when [Run Up Rate] is non-constant.
Technical LifeyrFalse1E+30≥0FalseTechnical lifetime of the Heat Plant
Unit Commitment Optimality-False-1In (-1,0,1,2,3)FalseUnit commitment integerization scheme for the Heat Plant.
Units-False1In (0,1)TrueNumber of Heat Plant units in service
VO&M Charge$/GJ (Metric), $/MMBtu (U.S. Imperial)False0FalseVariable operation and maintenance charge
WACC%False10≥0FalseWeighted average cost of capital
x-True0FalseValue to pass-through to solution
y-True0FalseValue to pass-through to solution
z-True0FalseValue to pass-through to solution

Heat Plant Fuels Input Properties

NameUnitsMulti-bandDefault ValueValidation RuleKey PropertyDescription
Heat RateGJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)True1FalseHeat-rate at load point (used with Load Point) or 'b' in the heat input function
Heat Rate BaseGJ/h (Metric), MMBtu/h (U.S. Imperial)False0FalseConstant term in fuel use function (no-load cost)
Heat Rate IncrGJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)True1FalseAverage marginal heat-rate in band
Heat Rate Scalar-False1≥0FalseScalar on base heat plant heat rate function
Is AvailableYes/NoFalse-1In (0,-1)FalseIf the fuel is available for use by the generator
Max InputGJ (Metric), MMBtu (U.S. Imperial)False1E+30≥0FalseMaximum amount of fuel input to heat plant
Max Ratio-False1Between 0 And 1FalseMaximum fuel mix ratio
Min Ratio-False0Between 0 And 1FalseMinimum fuel mix ratio
Mutually ExclusiveYes/NoFalse0In (0,-1)FalseIf the Fuel cannot be mixed with other Fuels associated with this heat plant.
Ratio-False1Between 0 And 1FalseFixed fuel mix ratio

Heat Plant Start Fuels Input Properties

NameUnitsMulti-bandDefault ValueValidation RuleKey PropertyDescription
Offtake at StartGJ (Metric), MMBtu (U.S. Imperial)True0≥0FalseFuel required to start a unit

Heat Plant Heat Output Nodes Input Properties

NameUnitsMulti-bandDefault ValueValidation RuleKey PropertyDescription
Participation Factor-False1Between -1 And 1FalseProportion sent to the node

Heat Plant Constraints Input Properties

NameUnitsMulti-bandDefault ValueValidation RuleKey PropertyDescription
Fuel Offtake CoefficientGJ (Metric), MMBtu (U.S. Imperial)False0FalseCoefficient of fuel offtake
Heat Production CoefficientGJ (Metric), MMBtu (U.S. Imperial)False0FalseCoefficient of heat production
Units Generating Coefficient-False0FalseCoefficient on the number of units generating

Heat Plant Objectives Input Properties

NameUnitsMulti-bandDefault ValueValidation RuleKey PropertyDescription
Fuel Offtake CoefficientGJ (Metric), MMBtu (U.S. Imperial)False0FalseCoefficient of fuel offtake of the heat plant
Heat Production CoefficientGJ (Metric), MMBtu (U.S. Imperial)False0FalseCoefficient of heat production
Units Generating Coefficient-False0FalseCoefficient on the number of units generating

Heat Plant Conditions Input Properties

NameUnitsMulti-bandDefault ValueValidation RuleKey PropertyDescription
Fuel Offtake CoefficientGJ (Metric), MMBtu (U.S. Imperial)False0FalseCoefficient of fuel offtake in condition

Heat Plant Output Properties

NameSummary NameProperty GroupPhasesMulti-bandDescription
Annualized Build Cost - $000Annualized Build Cost - $000ExpansionLT PlanFalseAnnualized cost of units built
Average Heat Rate - GJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)Average Heat Rate - GJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseAverage heat rate
Build Cost - $000Build Cost - $000ExpansionLT PlanFalseCost of building a unit
Efficiency - GJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)Efficiency - GJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseEfficiency of heat production
Electrical Usage - MWElectrical Usage - GWhProductionLT Plan, MT Schedule, ST ScheduleFalseElectrical usage from the electric boiler
FO&M Cost - $FO&M Cost - $000ProductionLT Plan, MT Schedule, ST ScheduleFalseFixed operation and maintenance cost
Fuel Offtake - GJ (Metric), MMBtu (U.S. Imperial)Fuel Offtake - TJ (Metric), BBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseFuel offtake
Heat Production - GJ (Metric), MMBtu (U.S. Imperial)Heat Production - TJ (Metric), BBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseHeat production
Heat Production Cost - $Heat Production Cost - $000ProductionLT Plan, MT Schedule, ST ScheduleFalseHeat production cost
Installed Capacity - GJ/h (Metric), MMBtu/h (U.S. Imperial)Installed Capacity - GJ/h (Metric), MMBtu/h (U.S. Imperial)CapacityLT Plan, MT Schedule, ST ScheduleFalseInstalled capacity
Marginal Heat Rate - GJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)Marginal Heat Rate - GJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseMarginal heat rate at optimal heat production level
Operating Hours - hOperating Hours - hProductionLT Plan, MT Schedule, ST ScheduleFalseNumber of hours of operation.
Ramp - GJ/h (Metric), MMBtu/h (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseRate at which units are ramping
Ramp Down - GJ (Metric), MMBtu (U.S. Imperial)Ramp Down - GJ (Metric), MMBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseTotal ramping down
Ramp Up - GJ (Metric), MMBtu (U.S. Imperial)Ramp Up - GJ (Metric), MMBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseTotal ramping up
Retirement Cost - $000Retirement Cost - $000ExpansionLT PlanFalseCost of retiring the Heat Plant
SRMC - $/GJ (Metric), $/MMBtu (U.S. Imperial)SRMC - $/GJ (Metric), $/MMBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseShort-run marginal cost (Fuel + VO&M + Emissions)
Start & Shutdown Cost - $Start & Shutdown Cost - $000ProductionLT Plan, MT Schedule, ST ScheduleFalseCost of unit starts and shutdowns
Start Fuel Cost - $Start Fuel Cost - $000ProductionLT Plan, MT Schedule, ST ScheduleFalseCost of fuel for unit starts
Start Fuel Offtake - GJ (Metric), MMBtu (U.S. Imperial)Start Fuel Offtake - TJ (Metric), BBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseStart fuel offtake
Units Built Units BuiltExpansionLT PlanFalseNumber of Heat Plant units built in this year
Units Producing Heat ProductionLT Plan, MT Schedule, ST ScheduleFalseNumber of units producing heat
Units Retired Units RetiredExpansionLT PlanFalseNumber of Heat Plant units retired in this year
VO&M Cost - $VO&M Cost - $000ProductionLT Plan, MT Schedule, ST ScheduleFalseTotal variable operation and maintenance cost
x xPass-throughLT Plan, MT Schedule, ST ScheduleTrueValue to pass-through to solution
y yPass-throughLT Plan, MT Schedule, ST ScheduleTrueValue to pass-through to solution
z zPass-throughLT Plan, MT Schedule, ST ScheduleTrueValue to pass-through to solution

Heat Plant.Fuels Output Properties

NameSummary NameProperty GroupPhasesMulti-bandDescription
Cost - $Cost - $000ProductionLT Plan, MT Schedule, ST ScheduleFalseTotal cost of fuel used
Hours in Use - hHours in Use - hProductionLT Plan, MT Schedule, ST ScheduleFalseNumber of hours the Fuel is in use by the heat plant
Marginal Heat Rate - GJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)Marginal Heat Rate - GJ/GJ (Metric), MMBtu/MMBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseMarginal heat rate at optimal heat production level
Offtake - GJ (Metric), MMBtu (U.S. Imperial)Offtake - TJ (Metric), BBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseFuel offtake
Offtake Ratio - %Offtake Ratio - %ProductionLT Plan, MT Schedule, ST ScheduleFalseProportion of fuel used by the heat plant
Price - $/GJ (Metric), $/MMBtu (U.S. Imperial)Price - $/GJ (Metric), $/MMBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseFuel price
SRMC - $/GJ (Metric), $/MMBtu (U.S. Imperial)SRMC - $/GJ (Metric), $/MMBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseShort-run marginal cost (Fuel + VO&M + Emissions)

Heat Plant.Start Fuels Output Properties

NameSummary NameProperty GroupPhasesMulti-bandDescription
Cost - $Cost - $000ProductionLT Plan, MT Schedule, ST ScheduleFalseTotal cost of fuel used
Offtake - GJ (Metric), MMBtu (U.S. Imperial)Offtake - TJ (Metric), BBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseFuel offtake
Price - $/GJ (Metric), $/MMBtu (U.S. Imperial)Price - $/GJ (Metric), $/MMBtu (U.S. Imperial)ProductionLT Plan, MT Schedule, ST ScheduleFalseFuel price