MT Schedule LDC Type

Units:-
Default Value:1
Validation Rule:In (1,2,3,4,7)
Description:Create one LDC for each period of this type in the horizon.

MT Schedule LDC Type determines the period of each LDC. The attribute can take the following values:

Day (value = 1)
One LDC is calculated for each day of the planning horizon.
Week(value = 2)
One LDC is calculated for each week of the planning horizon.
Month (value = 3)
One LDC is calculated for each month of the planning horizon.
Year (value = 4)
One LDC is created for each year of the horizon.

The number of blocks (simulation periods) in each LDC is set by the Block Count attribute. The method used to slice the duration curve into blocks is controlled by the LDC Slicing Method.

See also: