The Storage Control Type column specifies the criteria to be used in scheduling the generation available for a given storage unit. The options are:
Price (or NULL) - The default control method is to use the price series in the pre-forecast and schedule discretionary generation energy in the highest set of hours in that week ahead forecast.
Demand - Will target generation for the highest demand hours of the week in the zone.
DemandNetMR - Will shape to zone demand net of the zone's must-run energy from non-commitment units.
PoolDemand - Will target generation for the highest demand hours of the week in the pool.
PoolDemandNetMR - Will shape to pool demand net of the pool's must-run energy from non-commitment units.
NOTE: If the FUEL reference is specified for this variable the value in the Fuel Table will be applied.
For more information, see Storage Resources.