Units: | $ |
Mode: | Input/Output |
Multi-band: | True |
Default Value: | 0 |
Validation Rule: | Any Value |
Key Property: | No |
Description: | Cost of building a unit |
Facility Build Cost is the 'overnight cost' of building a unit of the Facility for LT Plan.
The Build Cost can be defined in combination with Economic Life and WACC so that LT Plan computes an annuity as described in the article LT Plan. If Build Cost is defined without these parameters then the entire Build Cost is incurred in the period the unit is built. The cost is also treated as a lump sum, if the Economic Life is entirely inside the planning horizon and the value of WACC is not the same as the Discount Rate.
Facility | Property | Value | Units |
---|---|---|---|
Factory | Units | 0 | - |
Factory | Max Operating Level | 500 | - |
Factory | FO&M Charge | 25,000,000 | $ |
Factory | Max Units Built | 1 | - |
Factory | Build Cost | 750,000,000 | $ |
Factory | Economic Life | 25 | years |
Factory | WACC | 10 | % |
For the example in Table 1, note how the property Max
Units Built is used to define the number of units that can
be built. The Facility will not be considered for expansion
optimization unless this is defined.
Build Cost is a multi-band property. This allows you to model a stream of payments leading up to the time of build.
Facility | Property | Value | Units | Band |
---|---|---|---|---|
Factory | Build Cost | 150,000,000 | $ | 1 |
Factory | Build Cost | 150,000,000 | $ | 2 |
Factory | Build Cost | 450,000,000 | $ | 3 |
For the example in Table 2 a series of payments in three years
leads up to the commission date which It also implies the facility
that needs three years to be built.
Facility Build Cost as an output is the total cost of new builds and is calculated as:
Notice that the reported Build Cost is the 'overnight cost' considering the input Build Cost in all bands.
See also:
Note: