Units: | MW |
Mode: | Output Only |
Multi-band: | False |
Default Value: | |
Validation Rule: | |
Key Property: | No |
Description: | Total ramping down |
Generator Ramp Down is the total ramping down in the period, and is defined as:
Ramp Down = MAX (0, Generation(t-1) - Generationt )
where:
t indexes periods of the
simulation.
The t=0 value of Generation refers to the
previous simulation step and for step one it is set with the Initial
Generation property.
This is distinct from Ramp which reports the ramping rate in megawatts per minute.Ramp Down can be used in combination with Minutes of Ramp Down to determine the intensity of ramping down over any period.