Units: | $/kW/yr |
Mode: | Input Only |
Multi-band: | False |
Default Value: | 0 |
Validation Rule: | ≥0 |
Key Property: | No |
Description: | Penalty for a shortage of capacity reserves |
Region Capacity Shortage Price is an input to LT Plan and is the penalty for shortage of Capacity Reserves. It applies when Min Capacity Reserves, Min Capacity Reserve Margin, Min Native Capacity Reserve, and Min Native Capacity Reserve Margin is defined.
Example
In this example, the Capacity Reserve Margin is to be maintained at or above 15% with penalties for violating the limit.
Region | Property | Value | Units | Band | Date From | Date To | Timeslice | Data File |
---|---|---|---|---|---|---|---|---|
SA | Load | 0 | MW | 1 | Load.csv | |||
SA | Capacity Shortage Price | 500 | $/kW/year | 1 | ||||
SA | Min Capacity Reserve Margin | 15 | % | 1 |