Units: | - |
Mode: | Input/Output |
Multi-band: | False |
Default Value: | 0 |
Validation Rule: | Any Value |
Key Property: | No |
Description: | Fixed (exact) production |
Facility Fixed Production defines a fixed profile of Production from the facility i.e. it constrains the Production to be exactly this value subject to availability.
How the value of Fixed Production is interpreted depends on the Fixed Production Global setting. It controls whether the value is across all units at the facility or unit-by-unit.
Fixed Production over-rides other constraints such as Min Operating Level, Max Ramp Up, and Max Ramp Down.
In the example in Table 1 the facility will be dispatched to follow the given profile (15 in hour 1 of Monday and 25 on hour 2 Monday) and beyond that it will follow dispatch according to its costs.
Property | Value | Units | Band | Date From | Date To | Timeslice |
---|---|---|---|---|---|---|
Units | 1 | - | 1 | |||
Max Operating Level | 250 | - | 1 | |||
Fixed Production | 15 | - | 1 | W2,H1 | ||
Fixed Production | 25 | - | 1 | W2,H2 |
In the example in Table 2 the facility will follow a series of
values defined in the Data File
"FIXED" but only for the specific date ranges shown, other times
the dispatch is optimized normally.
Property | Value | Units | Band | Date From | Date To | Timeslice | Data File |
---|---|---|---|---|---|---|---|
Fixed Production | -1 | - | 1 | ||||
Fixed Production | 0 | - | 1 | Tuesday, 1 December 2009 06:00:00 | Tuesday, 4 May 2010 06:00:00 | FIXED | |
Fixed Production | 0 | - | 1 | Friday, 7 May 2010 06:00:00 | Saturday, 8 May 2010 06:00:00 | FIXED |
By default the Fixed Production constraint is a hard constraint
meaning that no violations are allowed. You can optionally make
the constraint 'soft' and introduce a penalty price with the
property Fixed
Production Penalty. The frequency, quantity and cost of
violations are reported in the properties:
Note that Fixed Production is automatically derated by the Facility
Forced Outage Rate
and Maintenance Rate
in non-chronological simulation phases e.g. when LT
Plan or MT Schedule are
using load duration curves. This is done to simulate the effect of
outages on the ability of the station to meet the Fixed Operating
Level requirement.
Facility Fixed Production is the Production attributable to the Fixed Production constraint, and is defined as:
Fixed Production = Production - Fixed Production Violation
See also: