This column is used to in conjunction with the Maintenance Study functionality. It must be set to TRUE to identify units to be automatically scheduled for maintenance unless the resource is already specified in an active Maintenance Schedule Table. A blank field will default to FALSE.
NOTE: By default, Aurora will extrapolate future outages during a standard run (Run Maintenance Study NOT checked) if the input Maintenance Schedule table (MST) does not cover the study period. To change this so that only specified outages are recognized, then Schedule Maintenance must be set to FALSE (or blank) and Maintenance Length and Maintenance Cycle must be blank.
Schedule Maintenance Column
For further assistance, please contact Aurora Support.