Remove Penalty Adders from Pricing

This switch controls if penalties are applied or not.

When this box is checked, the model will adjust the zonal pricing by removing the effect of the non-commitment penalty on uncommitted resources as well as the Min Gen Back Down Penalty on committed or must run resources. These penalty adders are used in the LP dispatch to honor commitment and must run parameters; if this switch is selected the model fixes resource output at the solved level before deriving zonal pricing without the direct effect of the adders.   

NOTE: It is recommended to select this setting when using the Chronological Method = Hourly Limit in constrained dispatch runs.

 Simulation Options

 Dispatch and Demand

 Remove Penalty Adders from Pricing


For further assistance, please contact Aurora Support.