Use Demand in All Areas for Hydro Shaping

This option will schedule system-wide hydro resources against system-wide demand. If this option is not selected the hydro shaping for each hydro set will be scheduled to satisfy the demand in the area or areas defined by the Hydro Vectors table for that hydro set. See Hydro Shaping Logic for more information.

NOTE: When using ramp rates with the Nodal Capability, the current hour’s constraints (maximum resource capability) will be based on the previous hour’s nodal output for each zonal resource that is mapped to one or more nodal generators.

 Simulation Options

 Resource

 Solution Settings

 Use Demand in All Areas for Hydro Shaping


For further assistance, please contact Aurora Support.