Reserve Index
Reserve Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Cost Allocation Model | - | False | 0 | In (0,1,2,3) | False | Reserve cost allocation method. |
Cut-off Size | MW | False | 0 | False | The size below which a generator will not be considered for a share in reserve costs | |
Duration | s | False | 0 | ≥0 | False | Time over which the required response must be maintained |
Dynamic Risk | Yes/No | False | -1 | In (0,-1) | False | If elements in the Generator Contingencies and Line Contingencies collections are considered for dynamic risk calculations |
Energy Usage | % | False | 0 | Between 0 And 100 | False | Percentage of reserve dispatched in energy market |
Energy Usage For Replacement | Yes/No | False | 0 | In (0,-1) | False | If Reserve energy usage is used for replacement reserve. |
Include in LT Plan | Yes/No | False | -1 | In (0,-1) | False | If the reserve is modelled in the LT Plan phase. |
Include in MT Schedule | Yes/No | False | -1 | In (0,-1) | False | If the reserve is modelled in the MT Schedule phase. |
Include in ST Schedule | Yes/No | False | -1 | In (0,-1) | False | If the reserve is modelled in the ST Schedule phase. |
Is Enabled | Yes/No | False | -1 | In (0,-1) | True | Flag if the reserve is enabled |
Max Provision | MW | False | 1E+30 | ≥0 | False | Maximum provision allowed for reserve class |
Min Provision | MW | False | 0 | ≥0 | False | Minimum required reserve |
Mutually Exclusive | - | False | 0 | In (0,1,2) | False | If generation capacity providing this reserve is mutually exclusive to other reserves |
Price | $/MW | False | 0 | False | Price | |
Price Cap | $/MWh | False | 1E+30 | False | Cap on Reserve Price for settlement | |
Price Floor | $/MWh | False | -1E+30 | False | Floor on Reserve Price for settlement | |
Risk Adjustment Factor | - | False | 1 | False | Proportion of contingency size (MW reserve/MW contingency) | |
Sharing Enabled | Yes/No | False | 0 | In (0,-1) | False | If sharing of reserve across the transmission network is enabled. |
Sharing Losses Enabled | Yes/No | False | 0 | In (0,-1) | False | If sharing of reserve accounts for transmission losses. |
Static Risk | MW | False | 0 | False | Additional static risk over and above dynamic risk | |
Timeframe | s | False | 1E+30 | ≥0 | False | Timeframe in which the reserve is required |
Type | - | False | 1 | In (1,2,3,4,5,6,7,8) | False | Reserve type |
Unit Commitment | Yes/No | False | 0 | In (0,-1) | False | If the set of Generators providing the Reserve is optimized or always includes all members of the Reserve Generators collection. |
VoRS | $/MW | False | -1 | False | Value of reserve shortage (-1 sets hard constraint) | |
x | - | True | 0 | False | Value to pass-through to solution | |
y | - | True | 0 | False | Value to pass-through to solution | |
z | - | True | 0 | False | Value to pass-through to solution |
Reserve Generators Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Effectiveness | - | False | 1 | ≥0 | False | Estimated reserve effectiveness (MW/MW) |
Initial Pump Load Raise Provision | MW | False | 0 | ≥0 | False | Pump load raise reserve provision at time zero |
Initial Raise Provision | MW | False | 0 | ≥0 | False | Generator raise reserve provision at time zero |
Max Pump Response | MW | False | 1E+30 | ≥0 | False | Maximum dispatchable pump load reserve response |
Max Pump Response Factor | % | False | 100 | ≥0 | False | Maximum dispatchable pump load reserve response as a proportion of pump load |
Max Replacement | MW | False | 1E+30 | ≥0 | False | Maximum replacement (non-spinning) reserve capability |
Max Replacement Factor | % | False | 100 | ≥0 | False | Maximum replacement (non-spinning) reserve capability as a proportion of generation capacity |
Max Response | MW | False | 1E+30 | ≥0 | False | Maximum spinning reserve response |
Max Response Factor | % | False | 100 | ≥0 | False | Maximum spinning reserve response as a proportion of generation capacity |
Max Sync Cond Response | MW | False | 1E+30 | ≥0 | False | Maximum synchronous condenser reserve response |
Max Sync Cond Response Factor | % | False | 100 | ≥0 | False | Maximum synchronous condenser reserve response as a proportion of generation capacity |
Min Provision | MW | False | 0 | ≥0 | False | Minimum reserve provision when generator is available |
Min Regulation Provision | MW | False | 0 | ≥0 | False | Minimum regulation reserve provision when units are in the regulation range |
Min Replacement Provision | MW | False | 0 | ≥0 | False | Minimum replacement reserve provision when units are off-line |
Min Spinning Provision | MW | False | 0 | ≥0 | False | Minimum spinning reserve provision when units are generating |
Offer Price | $/MW | True | 10000 | False | Reserve offer price in offer band | |
Offer Quantity | MW | True | 0 | ≥0 | False | Reserve offer quantity in offer band |
Pump Offer Price | $/MW | False | 0 | False | Dispatchable pump load reserve offer price | |
Replacement Offer Price | $/MW | True | 10000 | False | Replacement reserve offer price in offer band | |
Replacement Offer Quantity | MW | True | 0 | ≥0 | False | Replacement reserve offer quantity in offer band |
Response Ratio | - | False | 1 | ≥0 | False | Ratio that converts energy ramping to units comparable to reserve ramping units |
Sync Cond Offer Price | $/MW | False | 0 | False | Synchronous condenser reserve offer price |
Reserve Purchasers Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Offer Price | $/MW | True | 10000 | False | Interruptible load offer quantity | |
Offer Quantity | MW | True | 0 | False | Interruptible load offer price |
Reserve Nested Reserves Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Cascading | Yes/No | False | 0 | In (0,-1) | False | If the relationship between the reserves is cascading or not |
Reserve Batteries Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Charge Offer Price | $/MW | False | 0 | False | Charging reserve offer price | |
Effectiveness | - | False | 1 | ≥0 | False | Estimated reserve effectiveness (MW/MW) |
Max Charge Response | MW | False | 1E+30 | ≥0 | False | Maximum dispatchable charging load reserve response |
Max Charge Response Factor | % | False | 100 | ≥0 | False | Maximum dispatchable charging load reserve response as a proportion of charge load |
Max Replacement | MW | False | 1E+30 | ≥0 | False | Maximum replacement (non-spinning) reserve capability |
Max Replacement Factor | % | False | 100 | ≥0 | False | Maximum replacement (non-spinning) reserve capability as a proportion of generation capacity |
Max Response | MW | False | 1E+30 | ≥0 | False | Maximum reserve response |
Max Response Factor | % | False | 100 | ≥0 | False | Maximum reserve response as a proportion of generation capacity |
Min Provision | MW | False | 0 | ≥0 | False | Minimum reserve provision when generator is available |
Min Regulation Provision | MW | False | 0 | ≥0 | False | Minimum regulation reserve provision when units are in the regulation range |
Min Replacement Provision | MW | False | 0 | ≥0 | False | Minimum replacement reserve provision when units are off-line |
Min Spinning Provision | MW | False | 0 | ≥0 | False | Minimum spinning reserve provision when units are generating |
Offer Price | $/MW | True | 10000 | False | Reserve offer price in offer band | |
Offer Quantity | MW | True | 0 | ≥0 | False | Reserve offer quantity in offer band |
Response Ratio | - | False | 1 | ≥0 | False | Ratio that converts energy ramping to units comparable to reserve ramping units |
Reserve Power2X Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Max Response | MW | False | 1E+30 | ≥0 | False | Maximum reserve response |
Reserve Regions Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Load Risk | % | False | 0 | False | Percentage of region's load at risk | |
LOLP Target | % | False | 0 | Between 0 And 100 | False | Loss of Load Probability target for this region |
Reserve Line Contingencies Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Flow Back Coefficient | - | False | 0 | False | Multiplier on line flow in the counter reference direction in setting the contingency size (Risk ≥ Coefficient * Flow Back) | |
Flow Forward Coefficient | - | False | 0 | False | Multiplier on line flow in the reference direction in setting the contingency size (Risk ≥ Coefficient * Flow Forward) |
Reserve Constraints Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Provision Coefficient | MW | False | 0 | False | Coefficient of reserve provision | |
Risk Coefficient | MW | False | 0 | False | Coefficient of reserve requirement | |
Shortage Coefficient | MW | False | 0 | False | Coefficient of reserve shortage |
Reserve Objectives Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Provision Coefficient | MW | False | 0 | False | Coefficient of reserve provision | |
Risk Coefficient | MW | False | 0 | False | Coefficient of reserve requirement | |
Shortage Coefficient | MW | False | 0 | False | Coefficient of reserve shortage |
Reserve Conditions Input Properties
Name | Units | Multi-band | Default Value | Validation Rule | Key Property | Description |
---|---|---|---|---|---|---|
Provision Coefficient | MW | False | 0 | False | Coefficient of reserve provision | |
Risk Coefficient | MW | False | 0 | False | Coefficient of reserve requirement | |
Shortage Coefficient | MW | False | 0 | False | Coefficient of reserve shortage |
Reserve Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Available Response - MW | Available Response - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Total available reserve response |
Cleared Offer Cost - $ | Cleared Offer Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Cost of cleared offer bands. |
Cleared Offer Price - $/MWh | Cleared Offer Price - $/MWh | Production | LT Plan, MT Schedule, ST Schedule | False | Price of marginal offer band |
Cost - $ | Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Reserve cost paid to reserve providers |
Price - $/MW | Price - $/MW | Production | LT Plan, MT Schedule, ST Schedule | False | Price |
Provision - MW | Provision - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Reserve provision |
Risk - MW | Risk - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Risk |
Shortage - MW | Shortage - GWh | Production | LT Plan, MT Schedule, ST Schedule | False | Reserve shortfall |
Shortage Cost - $ | Shortage Cost - $000 | Production | LT Plan, MT Schedule, ST Schedule | False | Cost of Reserve Shortage. |
Shortage Hours - h | Shortage Hours - h | Production | LT Plan, MT Schedule, ST Schedule | False | Number of hours of shortage. |
Time-weighted Price - $/GJ (Metric), $/MMBtu (U.S. Imperial) | Time-weighted Price - $/GJ (Metric), $/MMBtu (U.S. Imperial) | Production | LT Plan, MT Schedule, ST Schedule | False | Time weighted average price of reserve. |
x | x | Pass-through | LT Plan, MT Schedule, ST Schedule | True | Value to pass-through to solution |
y | y | Pass-through | LT Plan, MT Schedule, ST Schedule | True | Value to pass-through to solution |
z | z | Pass-through | LT Plan, MT Schedule, ST Schedule | True | Value to pass-through to solution |
Reserve.Generators Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Available Response - MW | Available Response - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Available reserve response |
Cleared Offer Cost - $ | Cleared Offer Cost - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Cost of cleared offer bands. |
Cleared Offer Price - $/MWh | Cleared Offer Price - $/MWh | - | LT Plan, MT Schedule, ST Schedule | False | Price of marginal offer band |
Non-spinning Reserve Provision - MW | Non-spinning Reserve Provision - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Reserve provision by off-line units |
Provision - MW | Provision - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Reserve provision |
Pump Dispatchable Load Provision - MW | Pump Dispatchable Load Provision - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Reserve provision by pump dispatchable load |
Revenue - $ | Revenue - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Reserve revenue |
Spinning Reserve Provision - MW | Spinning Reserve Provision - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Reserve provision by spinning reserve |
Sync Cond Reserve Provision - MW | Sync Cond Reserve Provision - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Reserve provision by units in synchronous condenser mode |
Reserve.Generator Contingencies Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Risk - MW | Risk - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Contribution of Generator contingency to Risk. |
Shadow Price - $/MW | Shadow Price - $/MW | - | LT Plan, MT Schedule, ST Schedule | False | Shadow price of Generator contingency constraint. |
Reserve.Generator Cost Allocation Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Cost - $ | Cost - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Reserve cost allocated |
Reserve.Purchasers Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Available Response - MW | Available Response - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Available reserve response |
Cleared Offer Cost - $ | Cleared Offer Cost - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Cost of cleared offer bands. |
Cleared Offer Price - $/MWh | Cleared Offer Price - $/MWh | - | LT Plan, MT Schedule, ST Schedule | False | Price of marginal offer band |
Cost - $ | Cost - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Reserve cost |
Provision - MW | Provision - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Reserve |
Revenue - $ | Revenue - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Reserve revenue |
Reserve.Batteries Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Available Response - MW | Available Response - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Available reserve response |
Cleared Offer Cost - $ | Cleared Offer Cost - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Cost of cleared offer bands. |
Cleared Offer Price - $/MWh | Cleared Offer Price - $/MWh | - | LT Plan, MT Schedule, ST Schedule | False | Price of marginal offer band |
Provision - MW | Provision - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Reserve provision |
Revenue - $ | Revenue - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Reserve revenue |
Reserve.Battery Contingencies Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Risk - MW | Risk - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Contribution of Battery contingency to Risk. |
Shadow Price - $/MW | Shadow Price - $/MW | - | LT Plan, MT Schedule, ST Schedule | False | Shadow price of Battery contingency constraint. |
Reserve.Power2X Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Available Response - MW | Available Response - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Available reserve response |
Provision - MW | Provision - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Reserve provision |
Revenue - $ | Revenue - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Reserve revenue |
Reserve.Regions Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Risk - MW | Risk - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Contribution of Region [Load] to the Risk. |
Reserve.Line Contingencies Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Risk - MW | Risk - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Contribution of Line contingency to Risk. |
Shadow Price - $/MW | Shadow Price - $/MW | - | LT Plan, MT Schedule, ST Schedule | False | Shadow price of Line contingency constraint. |
Reserve.Markets Output Properties
Name | Summary Name | Property Group | Phases | Multi-band | Description |
---|---|---|---|---|---|
Cost - $ | Cost - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Cost of reserve purchases from the market |
Net Cost - $ | Net Cost - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Net cost of reserve purchases from the market |
Net Purchases - MW | Net Purchases - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Net reserve purchases from the market |
Net Revenue - $ | Net Revenue - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Net revenue from reserve sales in the market |
Net Sales - MW | Net Sales - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Net reserve sold into the market |
Purchases - MW | Purchases - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Reserve bought from the market |
Revenue - $ | Revenue - $000 | - | LT Plan, MT Schedule, ST Schedule | False | Revenue from reserve sales in the market |
Sales - MW | Sales - GWh | - | LT Plan, MT Schedule, ST Schedule | False | Reserve sold into the market |